How a reinforced concrete corbel and a continuous nib are designed with the STATIX corbel calculator on its Eurocode 2 route. It covers the strut-and-tie model of Annex J.3 and 6.5, the nodes and the tie, the horizontal force, the anchorage of the tie, the links, the bearing of 10.9.5, and nibs and half joints.
1. Learning outcomes
After this lesson you can:
tell a corbel from a short cantilever (J.3(1): ac < z0) and draw its strut-and-tie model (6.5, Figure J.5);
find the lever arm z0, the strut angle θ and the tie force Ftd with the horizontal force HEd, and check the strut and both nodes (6.5.2, 6.5.4);
anchor the main tie at the front and in the column (J.3(4), 8.4, 8.6) and choose the links by J.3(2) or J.3(3);
check the bearing: its stress, the net and the nominal bearing length (10.9.5) and the partially loaded area (6.7);
design a continuous nib as a corbel per metre, hang its load up into the beam (6.2.1(9)) and know the half-joint models (10.9.4.6);
say which checks on the page follow EN 1992-1-1, which are the page’s own choices, and which you do by hand.
What the corbel page’s Eurocode 2 route uses. One corbel on the face of a column, with up to four load points, or a corbel on each face (double-sided). You give the design load FEd (the page calls it Fv, ULS): work 1.35 Gk + 1.5 Qk by EN 1990 6.10 first. The page then uses HEd = the larger of your Fh and 0.2 FEd. The 0.2 FEd is the page’s own floor, common practice: EN 1992-1-1 gives no minimum, and 10.9.5.1(2)P asks for the restraint forces to be taken into account. Materials. fck (cylinder, 12 to 50 MPa) and fyk, γc 1.5, γs 1.15. αcc and αct are 1.0, the recommended values of 3.1.6, as on the pages of lessons 2 and 3; this page has no input for them. fctm from Table 3.1. Strut and tie. J.3(1) with Figure J.5 and 6.5: 1.0 ≤ tan θ ≤ 2.5 (a steeper strut is laid at tan θ = 2.5 by moving the load arm out to z0/2.5). The strut and the node at the foot of the corbel work at 0.6ν′fcd (eq. 6.56, ν′ = 1 − fck/250), the node under the plate at k2ν′fcd with k2 0.85 (eq. 6.61), the tie at fyd (6.5.3). The page takes moments about the lower node inside the column, as Figure J.5 draws it: arm ac + w/2, w = FEd/(b 0.6ν′fcd) (section 3 and Example A). Links and shear. J.3(2) with k1 0.25 and J.3(3) with k2 0.5; VRd,c by 6.2.2(1) with σcp = 0; FEd ≤ 0.5 b d ν fcd (eq. 6.5) without the β of 6.2.2(6). As,min of 9.2.1.1(1) and 4 % at most on the main tie: the page’s choice, a corbel taken as a short beam (J.3 gives no minimum). Anchorage. J.3(4): in the corbel from the inner face of the plate, in the column from the near-face column bars to the far face. 8.4 with η1 0.7 when h > 250 mm and α1 only (the other α at 1, on the safe side); a welded cross bar by 8.6(2) (Fwd = 0.5 Asfyd) or a loop (Table 8.1N, eq. 8.1); links by 8.5. Bearing. 10.9.5.2(2): fRd = 0.4 fcd dry, fbed ≤ 0.85 fcd bedded (give fbed under More inputs, or the row reads NOT CHECKED), 0.85 fcd on a steel plate; b1 ≤ 600 mm when dry (10.9.5.2(3)). The net length a1 by the row of Table 10.2 for a concentrated support (a beam), always with the 20 mm of an isolated member (10.9.5.3); the front edge a2 by Table 10.3; 6.7 with Ac1 = Ac0. Cover and fire. 4.4.1 (Table 4.4N for your exposure class, class S4, Δcdev 10 mm); EN 1992-1-2 Table 5.5 with the corbel taken as a simply supported beam.
Not checked: the distance a3 and the deviations Δa2, Δa3 of eq. 10.6, the edge distance of a bearing over loops (10.9.4.7), crack control (J.3(5)), the column under the corbel’s moment, continuous nibs (on this route the page says NOT CHECKED: EN 1992-1-1 has no nib clause) and half joints. Other annexes may use other values.
3. How a corbel works
When a bracket is a corbel. EN 1992-1-1 J.3(1) calls a bracket a corbel when the load line is closer to the column face than the lever arm z0 of its tie, ac < z0, and lets it be designed with a strut-and-tie model by 6.5. A longer bracket bends like a short cantilever: design it by 6.1 and 6.2. The load comes onto a bearing plate ac from the face; a horizontal force HEd acts on the top surface. hc is the depth at the column face.The strut-and-tie model of Figure J.5. The load goes down a concrete strut from the plate to a node at the foot of the corbel, in the column, and a steel tie along the top holds the top of the strut. Moments about the lower node give the tie force: Ftd z0 = FEd a + HEd (z0 + aH). Here a is the arm of FEd about the node and aH the height of the bearing surface above the tie. The tie carries HEd as well. The strut slope must lie between tan θ = 1.0 and 2.5 (J.3(1)), with θ measured from the tie: 45° to 68°, steeper than the 21.8° to 45° that 6.2.3 allows in a beam.Finding z0. The lower node is a compression node (6.5.4(4) a)). The page takes it hydrostatic: the same stress on every face, equal to the strut limit 0.6ν′fcd. The face that takes the horizontal force (a vertical face) is then x = (Ftd − HEd)/(bσRd,max) high, and its centre lies z0 = d − x/2 below the tie. Put that in the moment equation and z0 follows from a quadratic. If z0/a comes out above 2.5, the strut is too steep for J.3(1): the page then moves the load arm out to z0/2.5, which raises the tie force a little.Where the lower node sits. The node carries FEd down into the column, so its bottom face, which takes FEd, is w = FEd/(bσ) wide and must lie in the column: under the corbel’s soffit nothing pushes up. Figure J.5 draws the node inside the column. The arm of FEd about the node centre is then ac + w/2. The page does this: arm ac + w/2, or z0/2.5 when the strut would be steeper than tan θ = 2.5. Moments about a point on the column face, as some older texts take them, give an Ftd low by roughly FEd(w/2)/z0, and tie and anchorage results that are not on the safe side. Example A shows both.
4. The nodes, the tie, the links and the horizontal force
Stress limits. A strut that crosses cracks, with tension across it, is held to 0.6ν′fcd (6.5.2(2)), with the recommended ν′ = 1 − fck/250. A node is checked on its faces: up to k1ν′fcd where only struts meet, k2ν′fcd where one tie is anchored and k3ν′fcd where ties run two ways (6.5.4(4), recommended k values). 6.5.4(5) allows up to 10 % more in some cases, such as triaxial compression; the page does not take it. 6.5.2(3) also points to 6.2.2 and 6.2.3 when a strut runs straight from a load to a support, as in a corbel.The node under the plate. The tie is anchored here, so this is a compression-tension node (6.5.4(4) b), Figure 6.27). Two stresses are checked against k2ν′fcd: the bearing under the plate, FEd over the plate area, and the strut where it leaves the node. The strut is a1 sinθ + u cosθ wide, where a1 is the plate length and u = 2aH the height of the node round the tie. The page also keeps the strut end within the strut limit 0.6ν′fcd, on the safe side.Anchoring the main tie. J.3(4) asks for the tie to be anchored at both ends. At the front the length starts at the plate’s inner edge, so the bar has little room: a welded transverse bar (8.6) or a loop (Figure 8.1, mandrel by Table 8.1N and eq. 8.1) does the work. In the column the length counts from the vertical bars at the near face, and the bar runs to the far face, usually bent down. The basic length is lb,rqd = (φ/4)(σsd/fbd) (8.4.3), with fbd = 2.25η1η2fctd (8.4.2) and η1 = 0.7 for a top bar in a member over 250 mm deep. A welded cross bar of 14 to 32 mm takes Fbtd (eq. 8.8N, at most the weld strength Fwd), and σsd drops by Fbtd/As (8.6(2)). The anchorage is never less than lb,min (eq. 8.6).Links. A short corbel, ac ≤ 0.5hc, gets closed horizontal or inclined links of at least k1As,main in addition to the main tie (J.3(2), recommended k1 = 0.25). They hold the strut together against splitting. A longer one, ac > 0.5hc, needs closed vertical links of at least k2FEd/fyd only where FEd exceeds VRd,c of 6.2.2 (J.3(3), recommended k2 = 0.5). A note: Figure J.6 a) carries two labels: ΣAs,lnk ≥ As,main beside the links and As,lnk ≥ k1As,main below; the text gives only k1. The page checks the text, summing every leg of every link. SANS 10100-1 asks for half the main tie. Check what your National Annex says.Shear near the support. 6.2.2(6) lets the share of a load within 0.5d to 2d of a support be cut by β = av/2d when VRd,c is checked, provided the tie is fully anchored; its Figure 6.4 b) shows a corbel. The load without β must still pass eq. 6.5, the crushing limit of the concrete. 6.2.2(7) lets corbels be designed by strut and tie instead, which is the J.3 route. The page checks eq. 6.5 without β, and in J.3(3) compares FEd itself with VRd,c, on the safe side.The horizontal force. A precast beam on a corbel shrinks, creeps and moves with temperature. If its bearing cannot slide freely, it pulls on the corbel. 10.9.5.1(2)P asks for these restraint actions in the design of the members next to such a bearing, but EN 1992-1-1 gives no number. The page uses HEd = the larger of your Fh and 0.2 FEd, its own floor. HEd acts at the bearing surface, aH above the tie, so the tie takes HEd(z0 + aH)/z0. Separate bars welded to the bearing plate (Fh bars on the page, an option it takes from SANS 10100-1 6.2.4.2.4) can carry HEd itself (As,h ≥ HEd/fyd, anchored in the column); the main tie then keeps only FEda/z0 + HEdaH/z0.
5. Bearings, nibs and half joints
The bearing length (10.9.5.2(1), Figure 10.6). A simple bearing needs a nominal length a. It is the net length a1 plus a2, lost at the front of the supporting member (Table 10.3), plus a3, lost at the end of the supported member (Table 10.4). Add the deviations: Δa2 for the distance between supports (Table 10.5) and Δa3 = ln/2500 for the member length. An isolated member, one not tied to its neighbours, needs 20 mm more (10.9.5.3(1)P). The page checks a1 (with the 20 mm) against the plate length and a2 against the distance to the front; a3 and the deviations are yours.Bearing strength. Where nothing else is specified, 10.9.5.2(2) gives fRd = 0.4 fcd for a dry bearing and fbed ≤ 0.85 fcd otherwise, with fcd the lower of the two members. Without mortar or a pad to spread the load, the bearing width b1 counts up to 600 mm only (10.9.5.2(3)). The net length a1 = FEd/(b1fRd) is never less than the row of Table 10.2 for the support: line supports of floors and roofs, or concentrated supports such as beams. 10.9.4.3(3) asks for good workmanship at dry joints and keeps the mean stress between plane dry surfaces to 0.3 fcd; a soft pad that spreads sideways needs bars near the surfaces by eq. 10.5 (10.9.4.3(4), (5)). The page uses the beam row for every corbel, and 6.7 with no spread for the partially loaded area.Nibs. A continuous nib along a beam carries floor units, such as hollowcore, on a line bearing. EN 1992-1-1 has no nib clause; the page’s Eurocode 2 route says NOT CHECKED for a nib. Design it by hand as a corbel per metre run: the strut and tie of J.3 and 6.5, the tie anchored from the inner edge of the bearing, links by J.3(2) or (3), the bearing as a line support of Table 10.2. The load enters the beam near its bottom, so the beam’s links at that face must hang it up to the top, in addition to the links for shear (6.2.1(9)).Half joints. A beam end cut down to sit on a support, a dapped end, is designed by strut and tie (10.9.4.6). Figure 10.4 gives two models, which may be combined. In one, vertical links close to the re-entrant corner hang the reaction up into the full beam, and a horizontal tie in the nib holds the strut. In the other, inclined bars run from the top of the nib across the corner into the bottom of the beam. Each tie is anchored past its node. The corbel page does not design half joints; the nib of Example B uses the same ideas.Which code, and what is left to you. Every check row on the Eurocode 2 route names its EN 1992-1-1 (or EN 1992-1-2) clause. Some choices are the page’s own and are stated in its rows or warnings: the floor HEd ≥ 0.2 FEd, the tie minimum of a beam, the beam row of Table 10.2 and the 20 mm of an isolated member on every corbel. Two more come from SANS 10100-1: the link zone over the upper 2d/3 (6.2.4.2.5) and the Fh bars welded to the plate (6.2.4.2.4), an option that EN 1992-1-1 does not require. The page puts the lower node inside the column, as Figure J.5 draws it (the strut row and calc sheet section 2: arm a = ac + w/2, or z0/2.5; section 3). Nibs, half joints, the full eq. 10.6, the hanging steel in a beam that carries a nib, crack control and the column itself are yours. The bending schedule uses SANS 282 bar shapes on every route.
6. Example A: a corbel for a precast beam
The worked parts open with a university or college email, a student licence (statix.engineering/university/), a calculator pack or a paid plan. Sign in to open them.
7. Example B: a nib for hollowcore units
The worked parts open with a university or college email, a student licence (statix.engineering/university/), a calculator pack or a paid plan. Sign in to open them.
8. Do it in STATIX
The worked parts open with a university or college email, a student licence (statix.engineering/university/), a calculator pack or a paid plan. Sign in to open them.
9. Common mistakes
The worked parts open with a university or college email, a student licence (statix.engineering/university/), a calculator pack or a paid plan. Sign in to open them.
10. Exercises
The worked parts open with a university or college email, a student licence (statix.engineering/university/), a calculator pack or a paid plan. Sign in to open them.
11. Self-check quiz
The worked parts open with a university or college email, a student licence (statix.engineering/university/), a calculator pack or a paid plan. Sign in to open them.
12. Lesson 4 on one page
The worked parts open with a university or college email, a student licence (statix.engineering/university/), a calculator pack or a paid plan. Sign in to open them.
Next: Lesson 5, staircasesReinforced concrete stairs to EN 1992-1-1 with the staircase calculator: the flight and landings as a one-way slab, actions on plan, bending, shear and span/d of the waist, the bars at the kinks, and dog-leg stairs on landings that span across. Go to lesson 5
A worked example for learning, not a design. Check every value against the current code, your national annex and your own project, and have the design checked and signed by a registered professional engineer.